SSD_JoshuaWurtzel-8063.jpg

August 4, 2026

In early July 2026, two buckling columns at the former Pfizer headquarters conversion in Midtown Manhattan shut down five blocks, emptied nearby buildings, and relocated a school. No one was hurt. But the correction work will be substantial, and someone will pay for it.

That is where the litigation starts. New York City has more than 16,000 residential units in the office-conversion pipeline, and conversions are harder than ground-up construction—existing floor plates, existing structural systems, and new loads imposed on columns that were designed for something else. When one of these projects fails, the question is never just what went wrong. It is who bears the cost of putting it right, and that answer is set by contract, by a handful of New York doctrines, and by the insurance structures sitting behind both.

Here is how those disputes actually break down.

Who is responsible for correcting defective work?

Start with the construction contract, because in most cases it answers the question. Standard-form agreements obligate the contractor to correct nonconforming work at its own cost, usually for a defined period after substantial completion, and that obligation typically runs regardless of whether the owner’s representatives inspected and approved the work along the way. An owner’s inspection rights are not a waiver of the contractor’s performance obligation unless the contract says so.

The complication is the design team. If the work was built as designed and the design was wrong, the contractor’s correction obligation may not reach it. Under the doctrine that traces to the Supreme Court’s 1918 decision in United States v. Spearin, an owner that furnishes plans and specifications impliedly warrants that they are adequate, and a contractor that builds to those plans is generally not liable for the resulting defect. 248 U.S. 132, 136–37 (1918). And that implied warranty is not defeated by the boilerplate obligating the contractor to examine the site and check the plans. Id. at 137. So the first fight in any conversion failure is a design-versus-workmanship fight, and it determines which whose insurance responds—the contractor’s general liability policy or the architect’s and engineer’s professional liability policies.

Contractual indemnity sits on top of all of this. General Obligations Law § 5-322.1 voids as against public policy a construction-contract clause purporting to indemnify a party against liability caused by its own negligence, whether in whole or in part. But a clause that provides indemnification “to the fullest extent permitted by law” survives, because that language contemplates partial indemnification and limits, rather than expands, the indemnitor’s obligation. Brooks v. Judlau Contracting, Inc., 11 N.Y.3d 204, 210 (2008). Enforceability thus turns, in part, on whether the savings language is there and on how fault is allocated.

Can an owner refuse to pay for work that has to be torn out?

Generally yes. If work does not conform to the contract, the owner has no obligation to pay for it, and an owner facing demolition of noncomplying work has a strong position on both withholding progress payments and setting off the correction cost against the balance due.

But the remedy is bounded. Damages for defective construction are measured by the cost of replacement, unless the cost of completion would be grossly and unfairly out of proportion to the good to be attained—in which case the measure is the difference in value between the work as built and the work as promised. Jacob & Youngs, Inc. v. Kent, 230 N.Y. 239, 244 (1921). That exception is narrow, and it is available to a contractor only when performance was in good faith and the waste of replacement is genuine. An owner that tears out and rebuilds without documenting the nonconformity, or without giving the contractor the cure opportunity the contract requires, weakens its position as against the contractor. Notice provisions in these agreements are not formalities, and courts enforce them.

Can the owner sue the design team in tort, or only in contract?

The economic-loss rule bars negligence recovery when the claimed losses flow from damage to the very property that is the subject of the contract and no one was injured, and the bar reaches service providers including architects and engineers. Archstone v. Tocci Building Corp. of New Jersey, 101 A.D.3d 1059, 1061 (2nd Dep't 2012). An owner in privity with its architect sues in contract, and relabeling the claim as negligence does not expand what it can recover.

A second and analytically separate line of cases supplies the way an owner can sue parties with which it never contracted. Under the Court of Appeals’s decision in Ossining Union Free School District v. Anderson LaRocca Anderson, a professional owes a duty for economic injury to a non-contracting party when the bond between them is the functional equivalent of contractual privity—the professional was aware the work was for a particular purpose, a known party relied on it, and there was conduct linking the professional to that reliance. 73 N.Y.2d 417, 425 (1989). This is a near-privity malpractice theory, not a carve out from the economic loss rule, though the Second Department has confirmed that such a claim is not precluded by that rule. Michael Anthony Contracting Corp. v. Queens N.Y. Realty, LLC, 225 A.D.3d 848, 856 (2nd Dep’t 2024).

The distinction has practical bite on a conversion project, where the owner often has no contract with the subconsultant that performed the structural analysis. Satisfying the near-privity elements takes evidence built at the time—who knew the report was for the owner, who relied on it, and what conduct connected the two. In Ossining, it mattered that one engineer billed the district directly.

What claims do the evacuated neighbors have?

This is where a lot of exposure evaporates. Under the Court of Appeals’s decision in 532 Madison Avenue Gourmet Foods, Inc. v. Finlandia Center, Inc., businesses that lose income because a street is closed after a nearby structural failure generally cannot recover in negligence when they suffered no personal injury and no damage to their own property. 96 N.Y.2d 280 (2001). The Court of Appeals held that a landowner does not owe a duty to protect an entire urban neighborhood against purely economic loss, and treated the line at personal injury or property damage as the principled basis for apportioning liability. Id. at 291, 292.

The facts of 532 Madison Avenue Gourmet Foods, Inc. are close to what happened last month. In December 1997, the south wall of the 39-story tower at 540 Madison Avenue partially collapsed after construction work aggravated existing structural defects. 96 N.Y.2d at 286. The city closed 15 blocks, from 42nd to 57th Street, for roughly two weeks. Id. Neighboring retailers sued for lost sales and lost. Id. at 286–87.

Of course, claims by neighbors who did sustain physical damage are a different matter, as are private nuisance and trespass theories where there was a physical invasion.

What does a stop-work order do to the schedule and the financing?

More than most owners plan for. A DOB stop-work order does not just pause construction. It triggers the delay provisions of the construction contract, the completion covenants in the construction loan, and—for conversions relying on the 467-m tax exemption—a clock that does not stop running. Indeed, to be eligible for the section 467-m tax exemption, the project must be completed by December 31, 2039.

A structural failure that pushes a project past a completion deadline can thus destroy economics that had nothing to do with the failure itself. When the delay is attributable to defective work, that lost tax benefit is a consequential damage, and whether it is recoverable turns on the contract’s consequential damages waiver—a clause many owners may sign without reading and most contractors insist on.

What to do in the first thirty days

Preserve the evidence before it is demolished. Correction work destroys the proof of what failed, and an owner that removes and rebuilds without a documented joint inspection will litigate causation at a permanent disadvantage. Photograph, measure, retain the removed materials, and put every potentially responsible party on notice before the remediation starts.

Notice the insurers immediately—builder’s risk, general liability, and professional liability all have notice conditions, and late notice is the most common reason a claim of this kind gets denied. Read the consequential-damages waiver and the indemnity clause in your construction contracts. And retain your own structural expert rather than relying on the design team’s post-failure analysis, because that team is a potential defendant and its report will read that way.

*          *          *

Joshua Wurtzel is a partner at Schlam Stone & Dolan LLP in New York, where he heads the firm’s commercial real-estate litigation practice. He represents owners, developers, lenders, and contractors in leasing, lending, and constructions disputes in New York state and federal court. He was also recently quoted in the Commercial Observer’s July 24, 2026 article on the Pfizer building emergency and the litigation likely to follow.

Attorneys

Joshua Wurtzel